Construction Starts: Duff, CFI IF 2023, Siegel

Published: 24 April 2025

Please be advised that ´ó·¢²ÊƱƽ̨ has mandated CORENOV CONSTRUCTEURS to carry out the following project: 23-027 Duff, CFI IF 2023, Siegel

¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýRenovation of lab 615 including replacement of ceiling tiles, repairs to floors/walls, installation of new lab bench and sink

Construction start date: April 28, 2025

Planned construction end date: End of May 2025

Work schedule: Monday to Friday, 7 a.m. to 3 p.m.

Project Manager: wafaa.zinebi [at] mcgill.ca (Wafaa Zinebi)

Assistant Project Manager: marco.bocchini [at] mcgill.ca (Marco Bocchini)

Contact for building users: carmen.lampron [at] mcgill.ca (Carmen Lampron) /Ìýshawn.casey [at] mcgill.ca (Shawn Casey)

--------------------------------------------------------------------------------------------------------

Scope of work:

  • Replace ceiling tiles
  • Repair floors/walls
  • Installation of new lab bench
  • Installation of new sink
  • Installation of a hydrogen probe

Impact & mitigation (if applicable):

  • Freight elevator use by contractors has been constrained before 8:00am daily.
  • No significant impact on users.
  • Expect low to medium levels of noise.
  • Service shutdowns:
  • Some work may require service shutdowns (e.g., electrical, plumbing). Building users will be informed in advance of these closures.

Safety considerations:

  • Removal of ceiling tiles and furniture, repairs to walls and floors planned in lab 615 expected to be completed by end of May 2025.
  • All applicable safety measures for work involving these materials will be put in place and monitored by an external industrial hygiene consultant.

These include dust-containment methods such as setting up enclosures to isolate the work areas, where required, or using specialized vacuuming equipment.