Construction Starts: Duff, CFI IF 2023, Siegel

Please be advised that ´ó·¢²ÊƱƽ̨ has mandated CORENOV CONSTRUCTEURS to carry out the following project: 23-027 Duff, CFI IF 2023, Siegel
¶Ù±ð²õ³¦°ù¾±±è³Ù¾±´Ç²Ô:ÌýRenovation of lab 615 including replacement of ceiling tiles, repairs to floors/walls, installation of new lab bench and sink
Construction start date: April 28, 2025
Planned construction end date: End of May 2025
Work schedule: Monday to Friday, 7 a.m. to 3 p.m.
Project Manager:Â wafaa.zinebi [at] mcgill.ca (Wafaa Zinebi)
Assistant Project Manager:Â marco.bocchini [at] mcgill.ca (Marco Bocchini)
Contact for building users:Â carmen.lampron [at] mcgill.ca (Carmen Lampron) /Ìýshawn.casey [at] mcgill.ca (Shawn Casey)
--------------------------------------------------------------------------------------------------------
Scope of work:
- Replace ceiling tiles
- Repair floors/walls
- Installation of new lab bench
- Installation of new sink
- Installation of a hydrogen probe
Impact & mitigation (if applicable):
- Freight elevator use by contractors has been constrained before 8:00am daily.
- No significant impact on users.
- Expect low to medium levels of noise.
- Service shutdowns:
- Some work may require service shutdowns (e.g., electrical, plumbing). Building users will be informed in advance of these closures.
Safety considerations:
- Removal of ceiling tiles and furniture, repairs to walls and floors planned in lab 615 expected to be completed by end of May 2025.
- All applicable safety measures for work involving these materials will be put in place and monitored by an external industrial hygiene consultant.
These include dust-containment methods such as setting up enclosures to isolate the work areas, where required, or using specialized vacuuming equipment.